IEC 60598-1:2024, Edition 10.0 List Apparatus
TESTING AND MEASURINGEQUIPMENT/ALLOWED SUBCONTRACTING
IEC 60598-1:2024, Edition 10.0
Luminaires - Part 1: General requirements and tests
Abbreviations tobe used at the column “Equipment Classification”:
“R” Required
“S” Maybe subcontracted, see OD 2012
“SP” SpecializedFacility, see IECEE 02-2
“W” Witnesstesting in the categories “MED” and “MEAS”
“3PPS” Three Phase Power Supply required
Clause | Measurement/testing | Testing / measuring equipment / material needed | Equipment Classification |
6.5 | Test of marking | Piece of cloth / Water / Petroleum spirit | R |
7.4.4 | Lampholder pressure test | Test caps / Pressure device / Torque driver | R |
7.4.5 | Voltage across lampholders | High voltage probe / Oscilloscope | R |
7.7.7 | Multi-pole plug and socket | Force meter (30 N) / Timer | R |
7.9.2 | Insulating linings and sleeves tests | Heating cabinet | R |
7.10.2 | Openings in double or reinforced insulation | Test probe 13 of IEC 61032:1997, Figure 9 | R |
7.11.6 | Electro-mechanical contact system | Low voltage variable current power supply / Voltmeter / High voltage source | R |
7.12.1 | Screws and connections (mechanical) and glands testing | Test screwdriver or spanner / Test rods | R |
7.13.1 | Mechanical strength tests | Spring-operated impact test apparatus according to IEC 60068-2-75 (other suitable means giving equivalent results)/ Test screwdriver or spanner | R |
7.13.3
| Mechanical strength tests | Test probe 11 of IEC 61032:1997, Figure 7 / Force meter (30 N) | R |
7.13.4 | Mechanical strength tests | Tumbling barrel test equipment of IEC 60068-2-31:2008, 5.3 | R |
7.14.1 | Adjusting devices testing | Glass test shelves / Weighting device / Test apparatus for adjustable devices / Torque measuring equipment / Timer | R |
7.18.1 | Resistance to corrosion | Test solution / Heating cabinet / Humidity cabinet | R |
7.18.2 | Stress corrosion | Closeable glass vessel / Test solution / Heating cabinet / Facilities to wash samples after test | R |
7.20.1 | Resistance to vibrations for rough service luminaires | Vibration test equipment | S |
7.20.2 | Rough service luminaires | Steel sphere / Conditioning cabinet (e.g. freezer) / Inclined plane (6°and 15°) or angle measuring device | R |
7.22 | Attachment to lamps | Weighing device | R |
7.24 | Photobiological hazards | Equipment list of IEC 62471-7:2023 | S |
Alternative, for retinal blue light hazard only, the equipment list of IEC/TR 62778 | S | ||
7.26 | Short circuit protection test | Test chain / Weighting device | R |
7.27 | Terminal blocks with integrated screwless protective earthing contact | Force meter (20 N / 50 N) / Timer / Earthing test equipment (9.2.3) | R |
7.28 | Fixing of thermal sensing controls | Temperature change test instruments of | S |
7.32.3.6 | SPC overload test | AC power supply source / Variable loads / High-frequency spark generator | R |
7.34 | Electromagnetic fields | Equipment list of IEC 62493:2015 + AMD1:2022 | S |
7.35 | Protection against moving fan blades | Test probe B of IEC 61032:1997, Figure 2 / Test probe 19 of IEC 61032:1997, Figure 13 | R |
Hardness test equipment acc. to ISO 48-4:2018 / Equipment to measure peripheral speed | S | ||
8.2.10.3 | Pull and torque tests on cord anchorage | Cord anchorage tests apparatus (pull and torque) | R |
8.2.14 | Plug test | Continuity tester (Figure 34) | R |
8.3 | Internal wiring dimensions | Micrometer / Equipment for insulation thickness | R |
8.4 | Test of conductors having a reduced cross-sectional area | Thermometer / Thermocouples / Ammeter / Adjustable resistive load | R |
9.2.3 | Earth continuity test | Earthing test equipment | R |
10.2.5 | Protection against electric shock tests | Test probe B of IEC 61032:1997, Figure 2 / Test probe A of IEC 61032:1997, Figure 1 / Test circuit for safety during insertion (Figure 19) | R |
10.2.6 | Covers | Force meter (20 N / 80 N) | R |
10.2.7 | Capacitor discharge | Oscilloscope / Test probe B of IEC 61032:1997, Figure 2 | R |
11.2.2 | Tests for first characteristics IP numerals 2, 3 and 4 | Test probe B of IEC 61032:1997, Figure 2 / | R |
11.2.3 | Tests for first characteristic IP numeral 5 and 6 | Apparatus for proving protection against dust | R |
11.2.4 | Drip-proof luminaires testing | Apparatus for protection against water IPX1 and IPX2 | R |
11.2.6 | Rain-proof and splash-proof luminaires testing | Apparatus for protection against water IPX3 and IPX4 | R |
11.2.8 | Jet-proof and powerful jet-proof luminaires | Apparatus for protection against water IPX5 and IPX6 | R |
11.2.10 | Watertight luminaires | Apparatus for protection against water IPX7 | R |
11.2.11 | Pressure watertight luminaires | Apparatus for protection against water IPX8 | S |
11.2.8 | High pressure water jet-proof luminaires | Apparatus for protection against water IPX9 (15 °C / 80 °C) | S |
11.3.1 | Humidity tests | Humidity cabinet / Timer | R |
12.2.2 | Insulation resistance tests | Insulation resistance meter | R |
10.2.3 | Electric strength tests | High voltage test equipment | R |
12.3 | Touch current and protective conductor current test | Test setup (Figure G.1) / Measuring networks (Figures G.2, G.3 and G.4) / Test probe B of IEC 61032:1997, Figure 2 / Oscilloscope | R |
13.2.1 | Creepage distances and clearances measurements | Digital calliper (or equivalent) / Oscilloscope / Test probe B of IEC 61032:1997, Figure 2 | R |
13.2.1 | Reductions for creepage distances and clearances by the use of coating or potting | Equipment list of IEC 61347-1:2015, Annex P | S |
14.3.2 | Endurance tests | Thermal cabinet / Endurance test equipment / Multimeter / Wattmeter / Timer | R |
14.4.2 | Thermal tests | Draught-proof enclosure or alternative chamber/room / Thermometer / Thermocouples / Voltage stabilizer / Multimeter / Wattmeter / Wheatston bridge or suitable measuring instrument / Timer | R |
14.5.2 | Abnormal operation testing | Force meter (30 N) / Test circuit of Figure C.3 | R |
14.7.3 | Test for luminaires with temperature sensing controls internal/external to the ballast or transformer | Equipment List of IEC 61558-1:2017, 15.3, 20.8, 20.9 | R |
15.2.2 | Resistance to heat test | Heating cabinet / Ball pressure test apparatus | R |
15.3.2 | Resistance to flame test | Needle flame test apparatus | R |
15.3.3 | Resistance to ignition testing | Glow-wire test apparatus | R |
15.4.2 | Resistance to tracking test | Proof tracking test device | R |
16 | Screw terminals | Torque drivers / Test cables / Pull device / Micrometer / Timer | R |
17 | Screwless terminals | Pull device / Variable current source / Voltmeter / Heating cabinet / Timer / Test cables | R |
A.2 | Touch voltage measurement | Non-inductive resistance of 50 kΩ / Voltmeter | R |
W.2 | General test | Artificial source (Table W.1) – if used | S |
W.4.2 | Smal Batteries | Cylinder of ISO 8124-1:2022, 5.2 / Timer / Force meter (10 N /30 N / 50 N) / Test probe 11 of IEC 61032:1997, Figure 7 / Test fingernail of IEC 60335-1:2020, Figure 7 / Torque meter (2 Nm / 4 Nm) / Cylindrical metallic mass (1 kg / 80 mm) | R |
W.4.3 | Battery compartment fasteners | Force meter (20 N) / Timer | R |
W.4.5 | Short-circuit protection | Test probe 13 of IEC 61032:1997, Figure 9 / Resistance meter / Timer / Temperature measurement | S |
W.4.6.1 | General conditions for testing lithium-ion battery charging | Single pole resistive-capacitive low pass filter (cut-off frequency of 5 kHz ± 500 Hz) / Thermocouples / Voltmeter / Ammeter / Timer | S |
W.4.7 | Protection against overpressure for Li-ion batteries | Apparatus designed to deliver 20; 30; 50; 100 ml ± 10 % of air at an initial pressure of 2 070 kPa ± 10 % through a (2,85 ± 0,05) mm diameter orifice / Pressure gauge / Timer | S |
W.6.3 | Thermal test (abnormal operation) | Equipment as required in 14.5.2 | S |
W.6.4 | Lithium-ion charging systems – Fault conditions | Equipment list of IEC 61347-1:2015 and | S |